Developing a route for a new transmission line is a complex process. South Dakota has statutes and rules that guide the route development process and help minimize a project's impact to humans and the environment.

Downloadable maps

Click or tap on the numbered box closest to your location to view a detailed, downloadable PDF map of the proposed routes filed in the SD PUC facility permit.

Route development process

Input from landowners, community members, local leaders, Tribal representatives, and state and federal agencies as well as the project team's own expertise is critical as we develop and finalize a proposed route.

study area

We started by using data from publicly available sources and federal, state, and local agencies to define a study area. We considered existing utility corridors, existing land use, resource areas, and other data to help identify route opportunities to further refine the study area.

route corridors

The next step in the route development process was to identify a route corridor where a possible route could be located and identify preliminary route options. We developed route corridors based on public input, opportunities to minimize impacts, and where the new transmission line will need to connect into substations.

preliminary route

The preliminary route is a further narrowed area within the route corridor. Similar to the route corridor, we developed the preliminary route based on input gathered during public open houses, input from community members, local leaders, Tribal representatives, and state and federal agencies. These factors assisted the project team as we developed the proposed route for the facility permit application.

proposed route

The project team used data, information and public input we gathered throughout the route development process to develop a proposed route. We submitted a facility permit to the SD PUC on September 4, 2026.

View the permit application

proposed routes

SD PUC will issue a final determination on the route. View the Regulatory process page for more details.

Routing considerations

During the routing process, our team identified opportunities where routes and route alternatives could be located while understanding sensitivities or areas that would make routing difficult.

opportunities iconOpportunities

Linear features that are oriented in the direction of the project:

  • Field lines
  • Property lines
  • Section lines
  • Roads
  • Utility corridors

sensitivities iconSensitivities

Area resources or conditions that may require additional review and consideration:

  • Agricultural conflicts
  • Airports (public)
  • Cemeteries
  • Communication towers
  • Conservation areas/nature preserves
  • Contaminated areas
  • Cultural/historic resources
  • Forest
  • Hospitals
  • Levees/dams
  • Mines/quarries
  • Pipelines*
  • Planned development
  • Protected federal lands
  • Protected state lands
  • Railroads*
  • Recreation
  • Religious facilities
  • Residences
  • Scenic byways
  • Schools/daycares
  • Sensitive species
  • Streams/wetlands
*Linear features with additional study needed